Update on the New Shop Construction

Last week we installed the new bulk cryogenic tank and vaporizer system and tied it into our new 2”, 316L stainless steel distribution header. The system was leak tested and trial runs of the system showed it meets all design specification for flow and pressure drop and gas temperature at full flow. This week we started the installation of the new work benches and the 316L stainless steel distribution lines for the other calibration gases which will be piped to each work station.

 

IMG_20130411_113150_840 IMG_20130411_154530_423

               Tank Delivery                                               Tank Installation                              

 

 IMG_20130411_154513_338 IMG_20130415_105132_389

         Piping System Hook Up                               New Work Stations

 

IMG_20130415_105121_827 IMG_20130415_105108_885

Lawrence and Wayne                                  Brad and Tim